- In Our Community
- Galvanized Pipe Replacement Program
- Southside Integrated Pipe System (SIPS)
- Greenland Water Reclamation Facility
- Deercreek Sewer Inspection and Improvement Program
- Construction Terms
- Septic Tank Phase Out
- Move Over Law
- Project Outreach Contact Form
- Site Restoration
- Trenchless Technology
- Meet the Project Outreach Team
- Connecting to the JEA Vacuum Sewer System
- Home
- In Our Community
- Construction Projects
- Center Street, Cherokee Circle, Locust Street & Gilmore Street Water Improvement Project
Center Street, Cherokee Circle, Locust Street & Gilmore Street Water Improvement Project
Estimated Dates & Work Schedule
Anticipated End Date: 2024-02-01
Monday through Friday, 7:00 a.m. to 4:00 p.m.*
*In some circumstances, extended hours and weekends may be required.
Project Objective
As part of the Galvanized Pipe Replacement Program to modernize more than 200 miles of JEA’s existing potable water distribution system, JEA crews upgraded and replaced portions of the existing water lines on Center Street from Rosselle Street to the dead end, Cherokee Circle from Rosselle Street to Locust Street, Locust Street from Rosselle Street to Cherokee Circle South and Gilmore Street between Cherokee Street and Locust Street.
These pipes had approached the end of their useful service lives and were proactively replaced to ensure the reliability of the JEA water system in the area. This project also included the installation of two (2) new fire hydrants. This project will provide increased water pressure, enhanced fire protection and improved system reliability.
Construction Conditions
Construction primarily occurred in City of Jacksonville rights-of-way, roads, and easements.
Project Work Area Map
Restoration of the Project Area
Restoration of the project area typically begins 2-3 weeks after the project has been completed. Any existing grass, sprinklers, pavement, curb, gutter, driveways and/or sidewalks affected during construction will be returned to its pre-construction condition.
Contact
-
If you have any questions about the Center Street, Cherokee Circle, Locust Street & Gilmore Street Water Improvement Project, please contact JEA Project Outreach at (904) 665-7500 or email us at projectoutreach@jea.com.