Jacksonville Golf and Country Club Sewer Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2019-01-14
Anticipated End Date: 2019-01-18

Project Objective

JEA and our contractor (LMK Pipe Renewal) have rehabilitated portions of the sanitary sewer main and lateral connections that serve the Jacksonville Golf and Country Club neighborhood.  

LMK utilized a Trenchless Lining Technology for the majority of the work, which reduced the amount of time needed to complete the project. Prior to lining, the lines were cleaned with a low-velocity spray and once cleaned, the lines were televised. If the pipe retained sufficient structural integrity LMK proceeded with the lining process. 

Restoration of Project Area - Paving Update

JEA contractors will be in the area the week of January 14, 2019 (weather permitting) to complete paving. We are requesting that residents within the paving boundaries (indicated on the map below) remove all vehicles, equipment and trash receptacles until the resurfacing operation is complete. Residents will have limited access to driveways when the paving is taking place.

Jacksonville Golf and CC Map

Project Challenges

As with many construction projects, we have encountered unforeseen circumstances that have delayed completion of the project. In addition to adverse weather, we found more than twice the amount of individual laterals to clean and inspect, we encountered varying pipe sizes throughout the project.

In multiple areas of Hunt Club Road, Biggin Church Road and Cricket Cove Road, the pipe did not retain sufficient structural integrity for the contractor to proceed which resulted in additional rehabilitation by JEA crews using the “open cut” construction method.