JEA Headquarters Downtown Chilled Water Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2021-07-17
Anticipated End Date: 2022-02-28

Monday through Friday, 7:00 a.m. to 6:00 p.m.*

*In some circumstances, extended hours and weekends may be required. The project area will remain closed 24/7 throughout the project. 

Project Objective

A contractor working for JEA (TB Landmark) installed chilled water mains along W. Duval Street, N. Julia Street and E. Monroe Street that will serve the new JEA headquarters and provide future connections for the City of Jacksonville’s Ed Ball Building and Jacksonville Fire and Rescue Department (JFRD) headquarters.

Chilled water systems efficiently supply chilled water to commercial buildings from a central plant, underground supply and return distribution pipes. The chilled water is then utilized by each building to provide air conditioning through their onsite air-handling units. 

Construction Conditions

Construction primarily occurred in the City of Jacksonville rights-of-way, roads and easements.   