Lofton Oaks Water Treatment Facility Project

Project Objective

A contractor working for JEA (Sawcross, Inc.) is working on a project to upgrade the Lofton Oaks water treatment plant (WTF) located at 84262 St. Paul Boulevard in Nassau County, in the Lofton Oaks Subdivision. A recent review at the facility by our engineers determined that the equipment at the facility is nearing the end of its useful service life and should be upgraded and replaced accordingly. JEA is planning to perform a complete rehabilitation of the entire facility, investing in Nassau County’s JEA infrastructure.  

In the past, during periods of increased water demand (i.e. summer months) the Lofton Oaks WTF has been used primarily as a back-up to other nearby water plants to service the area. However, due to current upgrades and repairs at the other plants on what we refer to as the Lofton Oaks grid, the Lofton Oaks WTP has experienced increased demand and use over the past few years.  

Once in operation, this upgraded potable (drinking) water facility will treat, store and pump treated water into JEA’s distribution system, providing water service to Nassau County. The improvement of this water treatment facility will allow for future growth in Nassau County, while providing improved water pressure and system reliability to all of our customers in the area. 

  •  Estimated Completion Date:  January 2024*

*Date is subject to change

Construction Conditions

Work will primarily occur on the facility property located at 84262 Saint Paul Boulevard, and in Nassau County rights-of-way and utility easements. However, you may notice some increased vehicular traffic through the neighborhood to the plant and there may be some noise associated with this construction. Normal construction work hours will be Monday through Friday from 7:30 a.m. to 5:30 p.m. Monday through Friday. There may be occasions where extended hours or night and weekend work may occur.

This project will also include the demolition and construction of several components behind the fenced areas of the facility (outlined below).   

  • Demolish existing pump control building
  • Construct new high service pump control building with electrical room and ADA restroom
  • Construct new electric system and control system (repurposing components when possible)
  • Remove and replace existing aerator and enclosure
  • Demolish and reconstruct existing ground 75,000 gallon storage tank
  • Repurpose existing pumps and motors
  • Demolish and replace existing yard piping valves, ground piping valves, flow meters, and concrete well slabs at the potable water well
  • FPL will also be installing a new 480 KV service to the project site from Highway A1A to St. Paul’s Boulevard located in the existing right-of-way just off the pavement

This project will not impact your normal JEA water, sewer or electric service.  

Lofton Oaks Water Treatment Facility Project

Project Update - October 2, 2023

As part of this project, contractor crews will soon begin work to install a new sanitary sewer manhole on St. Paul Boulevard near the water treatment facility. For the safety of the crews and the general public, the contractor will be required to temporarily close and detour traffic on St. Paul Boulevard while this work is completed. Please see a map of the work area and detour below. 

ST. PAUL BOULEVARD TEMPORARY ROAD CLOSURE & DETOUR
Anticipated Start Date: Wednesday, October 11, 2023*
Estimated Completion Date: Friday, October 13, 2023*

*Dates are subject to change.

This work will take place primarily within Nassau County rights-of-way and easements. Residents and businesses will be provided access, and will be permitted to drive (with caution) within the work area. Please observe all construction signs, detours, temporary traffic signals, and general directions provided by the crews working on-site.

We appreciate your continued patience throughout this important infrastructure improvement project and apologize in advance for any inconvenience caused by this road closure and detour. This project will not impact your normal JEA water, sewer or electric service.  

Lofton Oaks Water Treatment Plant Project - Detour

Restoration of the Project Area

Restoration of the project area will begin after the new water main has been installed, tested and cleared for use. Upon completion of the project, any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be returned pre-construction condition.