Otter Run Water Treatment Facility Improvement Project

The goal of this construction project is to make the community even better by improving our service and reliability to your neighborhood. Start and Completion dates are subject to change and do not include final restoration of the project area. Thank you in advance for your patience!

Estimated Dates & Work Schedule

Anticipated Start Date: 2018-04-30
Anticipated End Date: 2019-10-31

Work will take place Monday through Friday from 7:00 a.m. to 5:00 p.m. Please note in some circumstances, weekend and evening hours may be necessary.

Project Objective

JEA continues work to upgrade the Otter Run Water Treatment Plant (WTP) located at 96119 Otter Run Drive. In the past, during periods of increased water demand (i.e. summer months) the Otter Run WTP has been used primarily as a back-up to other nearby water plants to service your area.

However, due to current upgrades and repairs at the other plants on what we refer to as the Lofton Oaks grid, the Otter Run WTP has experienced increased demand and use over the past few years. 

A review of the facility by our engineers determined that the water reservoirs at the plant were nearing the end of their service lives and should be upgraded or replaced accordingly.  We are currently performing a complete rehabilitation of the entire facility, investing in Nassau County’s JEA infrastructure.

Learn more about how JEA delivers more than 107 million gallons of water each day to our customers and find ways to conserve this valuable resource.

Project Update - September 2019

On Tuesday, September 10th, a contractor working for JEA will complete paving on Otter Run Drive directly in front of the facility. For the safety of crews and the general public, we will be required to temporarily close this portion of Otter Run Drive while paving is completed. We apologize for any inconvenience. Please see the detour map below. 

Otter Run Temporary Road Closure

Construction Scope

During this project, most of the construction will take place behind the fenced areas of the plant and equipment traffic will be confined to the dirt road located behind the facility. However, residents may notice some increased vehicular traffic through the neighborhood to the plant and there may be some noise associated with this construction.

This project will also include the demolition and construction of several components behind the fenced areas of the facility (outlined below).  

  • Demolish existing yard piping valves, ground piping valves, flow meters, and concrete well slabs at the two potable water wells
  • Demolish existing fiberglass aerator and enclosure
  • Demolish two (2) existing steel ground storage tanks (30,000 gallon and 36,000 gallon)
  • Demolish one (1) 5,000 gallon hydro pneumatic tank
  • Demolish three (3) existing high service pumps, associated piping, valves, and flow meter
  • Demolish existing sodium hypochlorite disinfection feed and storage system
  • Demolish existing electrical gear and communication equipment
  • Construct new electric system and control system
  • Construct new yard piping as required to accommodate the new equipment and structures
  • Construct new high service pump building with electrical room and ADA restroom
  • Construct one (1) new 100,000 gallon ground storage tank with new aerator
  • Install three (3) new high service pumps and one (1) new flow meter assembly
  • Install a new sodium hypochlorite feed and storage system for water treatment
  • Provide new fence and landscaping around the plant site

 

Landscaping and Fencing

As part of this work, the existing landscaping and overgrowth of vegetation will be removed early in the project and replaced with new fencing and additional landscaping towards the end of the project. 

Below are renderings of the new landscaping and fencing plan for this facility. 

Map of Project Area

Restoration of the Project Area

Restoration of Otter Run Drive will begin once the new sewer manhole and lines have been installed, tested and cleared for use. Final restoration of the entire project area including new fencing and landscaping will occur once the project is complete in October 2019*.