Main Street Water Treatment Facility Water and Sewer Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2020-10-01
Anticipated End Date: 2023-03-16

Monday through Friday 7 a.m. to 5:30 p.m.*

 

Project Objective

Work was completed to install a new 36-inch transmission water main from JEA’s Main Street Water Treatment Facility located on N. Main Street to a connection point at the intersection of Beaver Street and Franklin Street near the Jacksonville Fairgrounds at the Sports Complex. These new water lines connect to existing water transmission lines that will serve customers throughout our service territory creating critical redundancies in our water system.

As part of the work, a contractor installed a 36-inch water main under Arlington Expressway from Albert Street to E. Beaver Street just west of Franklin Street using a trenchless technology referred to as horizontal directional drilling or HDD.

Additionally, JEA installed several new raw water mains that connect our existing raw water wells located throughout Springfield to our Main Street Water Treatment Facility located on N. Main Street to help bolster water production.

JEA replaced some of the existing water and sanitary sewer lines throughout the project limits. This will increase customer reliability, water pressure and prevent future sewer cave-ins and roadway issues.

Please see the below map for the overall project route and limits. 

Overall Project Area Map

Main St Wells Project

Progress Photos

Main St Progress Photo 12.1.20 (1)

 

Main St Progress Photo 12.1.20 (2)

Main St Progress Photo 12.1.20 (3)

Construction Conditions

Construction primarily occurred in City of Jacksonville rights-of-way, roads, and easements. 

Restoration of the Project Area

Restoration of the project area typically begins 2-3 weeks after the new water and sewer mains have been installed, tested and cleared for use. Upon completion of the project, any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be returned to its pre-construction condition.