West Grid - Wilson to Ortega Farms Sewer Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2019-01-02
Anticipated End Date: 2020-08-14

Normal work schedule is Monday through Friday 7:00 a.m. to 5:00 p.m. Please note that in some circumstances, evening and weekend work hours may be necessary. Completion date includes final restoration of the project area. 

Project Objective

JEA has completed work to replace and upsize an existing 24-inch sewer transmission main which had reached the end of its service life. This pipe serves a large segment of Jacksonville’s west side, conveying approximately 3.6 million gallons a day of sewage to JEA’s nearby Southwest Water Treatment Facility. The new 30-inch sewer transmission main will provide better sewer service reliability and assist with future growth in the area.              

The new sewer transmission main was installed starting near the intersection of Ortega Farms Boulevard and Timuquana Road, north along Ortega Farms Road, cross Fishing Creek at the City’s Wayne B. Stevens Boat Ramp, continuing along Confederate Point Road, Cedar Hills Boulevard, Sunbury Avenue and ended at the southwest corner of  Wilson Boulevard and Aldington Drive.

Final Paving Update - July 2020

The contractor returned to complete final paving of the project area July 27, 2020 through July 31, 2020* from 7:00 a.m. to 5:00 p.m. daily.  Dates are approximate and depending on weather, are highly subject to change. 

  • Paving east bound lanes of Wilson Boulevard between Aldington Drive and Sudbury Avenue - Two east bound lanes temporarily closed and traffic redirected to the turn lane during paving (48-hour closure)*
    • Paving both lanes of Sudbury Avenue between Wilson Boulevard and Cedar Hills Boulevard - Single temporary lane closures during paving
      • Paving both lanes of Cedar Hills Boulevard between Sudbury Avenue and Blanding Boulevard - Single temporary lane closures during paving

        *Dates and times are highly subject to change.

        Paving Area Map

        West Grid Final Paving Project Area

        Overall Project Area Map

        West Grid NB

        Progress Photos - Ortega Farms Boulevard

        OrtegaFarms_1_4.28.20

        OrtegaFarms_2_4.28.20

        OrtegaFarms_3_4.28.20

        Progress Photo - Sewer By-pass Line on Ortega Farms

        West Grid Progress Photo 4.22

        Progress Photo - Sudbury Avenue

        Sudbury Progress Photo 10.17.19

        Progress Photo - Wilson Boulevard

        West Grid Progress Photo 7.25.19

        Progress Photo - Jack and Bore Under Blanding Boulevard

        Confederate Point JB

        Construction Conditions and Tree Trimming

        Construction will primarily occurred in the City of Jacksonville (COJ) and Florida Department of Transportation’s (FDOT) rights of way, roads and easements. The contractor began with mobilizing equipment and locating existing utilities within the project limits to locate the public rights of way and existing utilities (JEA, AT&T, Comcast, TECO Gas, etc.). 

        The contractor was required to temporarily close portions of roads to thru-traffic to complete the installation of the new sewer force main. These closures were necessary for the both the safety of the workers and the general public. Residents and businesses that reside within the project boundaries were provided access and were permitted to drive (with caution) within the construction area. There were times during the day when customers had limited access when the contractor was working directly in front of homes or businesses. The COJ’s Wayne B. Stevens Boat Ramp remained accessible during construction. 

        Tree trimming was required in areas with low-hanging tree branches in order to safely navigate equipment through the project area. 

        Restoration of Project Area

        Restoration of the project area will begin after the sewer line has been tested and cleared for use. Upon completion of the project, any existing pavement, concrete (sidewalks and driveways), grass, landscaping, or irrigation impacted during construction will be returned to its pre-construction condition.