Riverview (Phase 2) Water Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2018-06-25
Anticipated End Date: 2018-12-20

Contractor work hours will be Monday through Friday from 7 a.m. to 5 p.m.

NOTE: In some circumstances, evening and weekend work may be necessary.

Roads Affected

Harriet Avenue

Project Objective

Working in partnership with the City of Jacksonville, a contractor (TB Landmark Construction) working for JEA installed a new potable water line in the Riverview neighborhood. The funding for this project is provided by the City of Jacksonville and the construction will be managed by JEA. 
As part of the project, JEA installed a new water main, individual water services to the property line, water meter boxes and fire hydrants to improve area fire protection.

Phase 2 includes the installation of a new water line along Harriet Avenue Project.
Read more about all three phases of the project

More information will be provided to customers on the JEA connection process and grant programs through future town meetings and project mailings.

Construction Conditions

Construction occurred in the City’s streets, rights of way and easements. 

Restoration of the project area will be begin soon after the pipes have been installed throughout the project area. Any existing grass, curb, gutter, driveways, or sidewalks affected during construction will be returned to their preconstruction condition. 

Connecting to the New JEA Water System

Connection to the water system will be voluntary. Additional information will be provided to customers on the JEA connection process and grant programs through a future town meeting and project mailings that will be sent upon the project’s completion.

Interested property owners will be responsible for paying all JEA connection fees, on-site plumbing costs and obtaining associated permits required to make the connection from your home to JEA’s water line located in the right-of-way. JEA will install a new water meter once connection fees are paid. 

Utility Tap In Program (UTIP)

The City of Jacksonville understands that not all residents may be able to absorb the costs associated with connecting to the new JEA water system. Federal and/or State affordable housing funds are available through the City’s Housing and Community Development Division Utility Tap-In Program (UTIP).

This financial assistance is for qualified owner-occupied homeowners in the form of a deferred payment loan that pays for all the costs associated with the connection of your home to the JEA water system.

Learn more about the Utility Tap-In Program.

Restoration of the Project Area

Restoration of the project area will be begin soon after the pipes have been installed throughout the project area. Any existing grass, curb, gutter, driveways, or sidewalks affected during construction will be returned to their pre-construction condition.

Phase 2 Project Area Map

Riverview Phase 2 Project Area

Progress Photos