Lancaster Street Water Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2023-06-20
Anticipated End Date: 2023-11-30

Normal working hours are 7:00 a.m. to 5:00 p.m.*

*In some circumstances, crews may be required to work evenings, overnights, and weekends to avoid peak traffic periods while installing the new water line. 

Project Objective

As part of the Galvanized Pipe Replacement Program to modernize more than 200 miles of JEA’s existing potable water distribution system, JEA crews upgraded and replaced portions of the existing water lines on Lancaster Street from Riverside Avenue to the dead end of Lancaster Street, and Riverside Park Place from Oak Street to Riverside Avenue.  

These pipes had approached the end of their useful service lives and were proactively replaced to ensure the reliability of the JEA water system in the area. This project also included the installation of one (1) new fire hydrant. This project will provide increased water pressure, enhanced fire protection and improved system reliability. 

Construction Conditions

Construction primarily occurred in City of Jacksonville rights-of-way, roads, and easements.

Project Area Map

Lancaster Water Improvement Project Map

Restoration of the Project Area

Restoration of the project area typically begins 2-3 weeks after the new water line has been installed, tested and cleared for use. Any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be returned to its pre-construction condition.