Circuit 825 – Neptune Beach to Mayport Electric Reliability Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2024-02-26
Anticipated End Date: 2024-04-10

Monday through Friday, 9:00 a.m. to 4:00 p.m.* 

*In some circumstances, extended hours and weekends may be required. 

 

Project Objective

JEA contractor crews (SPE) replaced some of the electric transmission infrastructure that spans from the JEA electric substation in Neptune Beach to the JEA electric substation in Mayport. This work included the replacement of approximately 3.4 linear miles of static (shield) wiring. This project will provide better power quality and reliability to the area.

Construction Conditions

Construction primarily occurred along the city’s rights-of-ways and utility easements.

Restoration of the Project Area

Restoration of the project area typically begins 2-3 weeks after the has been completed. Any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be returned to its pre-construction condition. 

Project Work Area Map

Circuit 825 – Neptune Beach to Mayport Electric Reliability Project - Mayport Road Lane Closure Map