Arlington East Wastewater Treatment Plant Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2021-06-14
Anticipated End Date: 2022-07-31

Monday through Friday, 7:00 a,m. to 5:00 p.m.*

*NOTE: In some circumstances, evening and weekend work hours may be required.

Project Objective

JEA completed a project to upgrade our Arlington East Water Treatment Facility located at 1555 Millcoe Road. These upgrades included enhanced odor controls (new instrumentation and controls panels, piping and pumps). Once the new odor control systems have been installed, tested and cleared for use, the old odor control systems will be decommissioned.  

Construction Conditions

The majority of construction took place behind the fenced areas of the facility. Residents may notice increased traffic and noise associated with construction activities during working hours.