Van Gundy Road Water Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2025-10-27
Anticipated End Date: 2026-03-31

*Dates are highly subject to change. Crews will not work on JEA holidays.

Project Objective

As part of the Small Diameter Pipe Replacement Program to modernize hundreds of miles of JEA’s existing potable water distribution system, JEA will soon begin a project in your area to replace and upgrade portions of the water lines on Van Gundy Road from West Montcalm Drive to Winton Drive, Cartier Circle from Champlain Road to Cavalier Road, and Seine Drive from Champlain Road to Cavalier Road.

Construction Areas

Work will primarily occur in City of Jacksonville rights-of-way and easements.

Construction Conditions

Residents and businesses will have access and will be permitted to drive (with caution) within the project area. There may be times when driveway access is limited while crews are working directly in front of homes and/or businesses. Please observe all construction signs, detours, and general directions provided by the crews working on-site.

Planned Water Outages

Some customers may experience minor interruptions to their water service. JEA will notify customers at least 48 hours prior to any planned water outages.