Osceola Street Water Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2023-05-22
Anticipated End Date: 2024-01-09

Monday through Friday, 7:00 a.m. to 4:00 p.m.*

*In some circumstances, extended hours and weekends may be required. 

Project Objective

As part of the Galvanized Pipe Replacement Program to modernize more than 200 miles of JEA’s existing potable water distribution system, JEA replaced and upgraded portions of the water lines on Osceola Street, Dellwood Avenue and Myra Street. 

These pipes had approached the end of their useful service lives and were proactively replaced to ensure the reliability of the JEA water system in the area.  

This project also included the installation of two (2) new fire hydrants. This project will provide increased water pressure, enhanced fire protection and improved system reliability.

Construction Conditions

Construction primarily occurred in City of Jacksonville rights-of-way, roads, and easements.

Restoration of the Project Area

Restoration of the project area typically begins 2-3 weeks after the project has been completed. Any existing grass, sprinklers, pavement, curb, gutter, driveways and/or sidewalks affected during construction will be returned to its pre-construction condition. 

Overall Project Area Map

Osceola Street Water Project Map