West Grid - Wilson to Ortega Farms Sewer Improvement Project

The goal of this construction project is to make the community even better by improving our service and reliability to your neighborhood. Start and Completion dates are subject to change and do not include final restoration of the project area. Thank you in advance for your patience!

Estimated Dates & Work Schedule

Anticipated Start Date: 2019-01-02
Anticipated End Date: 2020-05-31

Normal work schedule is Monday through Friday 7:00 a.m. to 5:00 p.m. Please note that in some circumstances, evening and weekend work hours may be necessary. 

Project Objective

JEA is continuing work to replace and upsize an existing 24-inch sewer transmission main which has reached the end of its service life. This pipe serves a large segment of Jacksonville’s west side, conveying approximately 3.6 million gallons a day of sewage to JEA’s nearby Southwest  Water Treatment Facility. When completed, this new 30-inch sewer transmission main will provide better sewer service reliability and assist with future growth in the area.              

The new sewer transmission main will be installed starting near the intersection of Ortega Farms Boulevard and Timuquana Road, north along Ortega Farms Road, cross Fishing Creek at the City’s Wayne B. Stevens Boat Ramp, continuing along Confederate Point Road, Cedar Hills Boulevard, Sunbury Avenue and ending at the southwest corner of  Wilson Boulevard and Aldington Drive.

Temporary Lane Closure Sudbury Road - Rendale Drive North to Wilson Boulevard

For the safety of our crews and the general public, crews will be required to temporarily close a portion of Sudbury Avenue from Rendale Drive North to Wilson Boulevard for approximately one month beginning August 30th. This closure will run concurrently with Temporary Lane Closure #3 on Wilson Boulevard. 

Detour Map - Sudbury

Temporary Road Closure - Cedar Hills Boulevard from Sudbury Avenue to Blanding Boulevard

For the safety of our crews and the general public, JEA will be required to temporarily close a portion of Cedar Hills Boulevard from Sudbury Avenue to Blanding Boulevard from October 23rd through November 13th* while the new sewer line is being installed in the center of the roadway. 

Traffic will be detoured to Jammes Road and Wilson Boulevard during the temporary road closure. Please observe all construction signs, detours and general directions provided by the crews working on site. We apologize in advance for delays caused by this work. Please see the below map for details. 
Cedar Hills Detour Map

Overall Project Detour

The contractor will continue to detour traffic along Ortega Farms Boulevard as the pipe installation continues gradually down the road. Please pay close attention to electronic message boards as detour information will be updated. 

Detour Map - West Grid

Project Area Map

West Grid NB

Progress Photo - Wilson Boulevard

West Grid Progress Photo 7.25.19

Progress Photo - Jack and Bore Under Blanding Boulevard

Confederate Point JB

Progress Photo - Sudbury Avenue

Sudbury Progress Photo 10.17.19

Construction Conditions and Tree Trimming

Construction will primarily occur in the City of Jacksonville (COJ) and Florida Department of Transportation’s (FDOT) rights of way, roads and easements. The contractor will begin with mobilizing equipment and locating existing utilities within the project limits to locate the public rights of way and existing utilities (JEA, AT&T, Comcast, TECO Gas, etc.). 

The contractor will be required to temporarily close portions of roads to thru-traffic to complete the installation of the new sewer force main. These closures are necessary for the both the safety of the workers and the general public. Residents and businesses that reside within the project boundaries will be provided access and are permitted to drive (with caution) within the construction area. There will be times during the day when customers may have limited  access when the contractor is working directly in front of homes or businesses. The COJ’s Wayne B. Stevens Boat Ramp will remain accessible during construction. 

Tree Trimming

Tree trimming will be required in areas with low-hanging tree branches in order to safely navigate equipment through the project area. 

Restoration of Project Area

Restoration of the project area will begin after the sewer line has been tested and cleared for use. Upon completion of the project, any existing pavement, concrete (sidewalks and driveways), grass, landscaping, or irrigation impacted during construction will be returned to its pre-construction condition.