Richmond Park Drive East Sewer Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2022-04-25
Anticipated End Date: 2022-05-20

Monday through Friday, 7:00 a.m. to 5:00 p.m.*

*In some circumstances, evening hours and weekends may be required. 

Project Objective

JEA crews replaced and upgraded a portion of failing sanitary sewer line located near 4118 Richmond Park Drive East. This repair was necessary to ensure the reliability of the sewer system that serves the area. Failures to sewer lines can potentially cause major sewer back-ups, environmental harm and roadway issues. 

Construction Conditions

For the safety of our crews and the general public, we were required to temporarily close and detour traffic around the work area while this work was completed.  

Richmond Park Dr E Sewer Improvement Project Map

Restoration of the Project Area

Restoration of the project area will typically begin 2-3 weeks after the new sewer main has been installed, tested and cleared for use. Upon completion of the project, any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be returned pre-construction condition.