Estimated Dates & Work Schedule
Anticipated Start Date: 2019-09-25
Anticipated End Date: 2020-02-28
Anticipated End Date: 2020-02-28
Monday through Friday, 7:00 a.m. to 5:00 p.m. NOTE: In some circumstances, weekends and evening hours may be necessary.
Project Objective
Working in partnership with the City of Jacksonville, JEA installed sixty-six (66) new stand-alone wooden poles with LED streetlights along Soutel Drive from New Kings Road to Lem Turner Road. These new lights will be energy efficient and will provide for a brighter and safer community.