Small Diameter Pipe Replacement Program

Program Overview

JEA developed the Small Diameter Pipe Replacement Program to modernize hundreds of miles of JEA's existing potable water distribution system to reduce service failures and meet current potable flow standards. JEA estimates that more than 70 percent of its water main breaks and leaks are a result of galvanized pipes that are either at or rapidly approaching the end of their useful life, putting a considerable strain on JEA’s maintenance operations. Although JEA has always replaced failing pipes as part of its maintenance activities, this program accelerates progress by providing dedicated funding and management focused on execution.

By replacing the existing, inadequate galvanized mains, JEA's customers will enjoy greater reliability, improved water pressure and increased fire protection with the introduction of hydrants in currently unserved or underserved areas. At the same time, JEA will realize reduced maintenance costs by minimizing the potential for future line failures.

So far, JEA has replaced over 200 miles of old pipes throughout Jacksonville.


Small Diameter Pipe Replacement Projects

Currently, the Small Diameter Pipe Replacement Program includes water projects in design totaling 45,858 linear feet and more than 141,552 linear feet of projects in the project definition phase. It is estimated that by the end of 2025, JEA will have replaced nearly 116,270 linear feet (more than 22 miles) of aging 2-inch galvanized pipe in neighborhoods throughout Jacksonville.

Continuous assessment of small-diameter pipe performance within JEA’s water and sewer systems is essential to maintaining reliable service. Concurrent with planning, design, and construction on existing projects, JEA is analyzing break and service data to identify future replacements. The selection process includes a thorough evaluation of factors such as the number and density of line breaks, number of properties served, and proximity to larger water mains. Through this process, JEA methodically prioritizes projects that will have the greatest positive impact on customers and maintenance operations. Over the next several years, JEA will invest millions of dollars in neighborhoods across Jacksonville to provide modernized, dependable water service.

Small Diameter Pipe Replacement Program Timeline 2026

Planning, Design and Construction Projects

Pre-design planning begins when street segments are selected for inclusion in the program. This involves surveying the streets and surrounding areas to determine the precise location of the existing galvanized pipe and other underground utilities that may present conflicts during construction. The pre-design evaluation will also identify the public rights of way, existing asphalt and soil conditions, and other conditions that will be factored into the project’s design.

After the design is completed, projects are constructed using a combination of local contractors and JEA crews dedicated to this program. Some street segments are “packaged” as a single project to be constructed at the same time due to their connectivity and proximity. Those projects are bid and awarded to a contractor. Smaller, individual street segments are completed by JEA’s in-house forces. This bilateral approach gives JEA the flexibility to keep projects moving forward at a consistent pace.

Examples of Construction Conditions on a Small Diameter Pipe Replacement Project 

Below is an example of what type of work you may see crews performing on a water improvement project. Once the new water line is installed, tested and cleared for use, we will return soon after to complete restoration of the project area. Restoration of the project area typically begins 2-3 weeks after the project has been completed. Any existing grass, sprinklers, pavement, curb, gutter, driveways and/or sidewalks affected during construction will be returned to its pre-construction condition. 

Small Diameter Pipe Replacement Project Progress Photo 1

Small Diameter Pipe Replacement Project Progress Photo 2

Small Diameter Pipe Replacement Project Progress Photo 3

Small Diameter Pipe Replacement Project Progress Photo 4

Small Diameter Pipe Replacement Project Progress Photo 5

Small Diameter Pipe Replacement Project Progress Photo 6

Small Diameter Pipe Replacement Project Progress Photo 7

JEA Water Project Example


View Projects Currently Under Construction

McConihe Water Improvement Project

Leonard Circle Water Improvement Project

Townsend Boulevard Water Improvement Project

Verona Avenue Water Improvement Project

State Street Water Improvement Project

Van Gundy Water Improvement Project