Princess Anne Lane and Prince Edward Road Water Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2025-06-04
Anticipated End Date: 2026-07-31

Monday through Friday, 7:00 a.m. to 5:00 p.m.* 

*In some circumstances, extended hours and weekends may be necessary. 

Project Objective

As part of the Small Diameter Pipe Replacement Program to modernize more than 200 miles of JEA’s existing potable water distribution system, JEA replaced and upgraded portions of the water lines on Princess Anne Lane, Avon Drive, Carlisle Road from Avon Drive to Waverly Lane, King Richard Road from Avon Drive to Waverly Lane, Prince Edward Road from Carlisle Road to Charlemagne Road, Malpas Lane, Maid Marian Lane, and Yacht Club Road from Prince Edward Road to King Richard Road. This project also included the installation of two (2) new fire hydrants.

This project will provide increased water pressure, improved system reliability and enhanced fire protection to the area.

Construction Conditions

Construction primarily took place in the City of Jacksonville rights-of-way and utility easements.

Project Area Map

  Princess Anne WIP

Restoration of the Project Area

Restoration of the project area typically begins 2-3 weeks after the project has been completed. Any existing grass, sprinklers, pavement, curb, gutter, driveways and/or sidewalks affected during construction will be returned to its pre-construction condition.