Forbes Street Water Service Installation Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2024-08-21
Anticipated End Date: 2025-04-30

Monday through Friday, 7:00 a.m. to 5:00 p.m.*

*Extended hours and weekends may be required throughout the project duration. 

Project Objective

As part of the Galvanized Pipe Replacement Program to modernize more than 200 miles of JEA’s existing potable water distribution system, JEA crews have reviewed water services and relocated service connections to larger water mains on Forbes Street between Stockton Street and Margaret Street. This project will provide increased water pressure and improved system reliability.

Construction Conditions

Construction primarily occurred in City of Jacksonville rights-of-way, roads, and easements. 

Restoration of the Project Area

Restoration of the project area typically begins 2-3 weeks after the project has been completed. Any existing grass, sprinklers, pavement, curb, gutter, driveways and/or sidewalks affected during construction will be returned to its pre-construction condition. 

Project Area Map

Forbes Street Water Renewal Project