- Home
- In Our Community
- Construction Projects
- Breve Drive Water Improvement Project
Breve Drive Water Improvement Project

Estimated Dates & Work Schedule
Anticipated End Date: 2025-05-30
Monday through Friday, 7:00 a.m. to 5:00 p.m.*
*In some circumstances, extended hours and weekends may be required.
Project Objective
As part of the Small Diameter Pipe Replacement Program to modernize more than 200 miles of JEA’s existing potable water distribution system, a contractor working for JEA (T.G. Utility Company) recently completed work to replace and upgrade portions of the water lines on Breve Drive, Belafonte Drive, Mahalia Drive, Dakota Drive, Eartha Drive and Poitier Drive.
These pipes were approaching the end of their useful service lives and are being proactively replaced to ensure the reliability of the JEA water system in the area. This project will provide increased water pressure, enhanced fire protection and improved system reliability.
Construction Areas
Work will primarily occur in City of Jacksonville rights-of-way and easements.
Temporary Road Closures - Paving Notice - May 21st to June 1st
A paving subcontractor is scheduled to return to complete paving in the project area. For the safety of both crews and the public, temporary road closures and traffic detours will be in place while paving is actively underway. Please refer to the map below for the specific work area.
We kindly ask all residents within the paving zone to remove vehicles, equipment, and trash receptacles from the street during the dates and times listed below. Access to streets and driveways in the immediate work area will be limited during this time. Roadway access will be restored at the end of each workday. Please note that any vehicles left on the street during the posted work hours may be towed.
TEMPORARY ROAD CLOSURES – PAVING NOTICE:
Anticipated Start Date: May 21, 2025*
Estimated Completion Date: June 1, 2025*
Paving Schedule: Monday – Friday, 7:00 a.m. to 5:00 p.m.*
*Dates and times are weather permitting and highly
subject to change.
This work will occur along the City of Jacksonville rights-of-way and utility easements. Residents and/or businesses will be provided access to their driveways and will be permitted to drive (with caution) around the work area. There may be times when driveways are temporarily blocked while crews are paving directly in front of homes or businesses.
Please observe all construction signs, detours and general directions provided by the crews working on-site.
Project Area Map
Restoration of the Project Area
Restoration of the project area will begin soon after the project has been completed. Any existing grass, sprinklers, pavement, curb, gutter, driveways and/or sidewalks affected during construction will be returned to its pre-construction condition.
Contact
-
If you have any questions about the Breve Drive Water Improvement Project, please contact JEA Project Outreach at (904) 665-7500 or email us at projectoutreach@jea.com.