Allandale Circle East Water Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2025-03-12
Anticipated End Date: 2025-05-22

Monday through Friday, 7:00 a.m. to 5:00 p.m.*

*In some circumstances, extended hours and weekends may be necessary. 

Project Objective

As part of the Small Diameter Pipe Replacement Program to modernize more than 200 miles of JEA’s existing potable water distribution system, JEA crews replaced portions of the existing water main on Allandale Circle North, Allandale Circle South, Allandale Circle East, Prospect Street and Prospect Street East. This work also included the installation of four (4) new fire hydrants.

This project will provide increased water pressure, improved system reliability and enhanced fire protection to the area. 

Construction Conditions

Construction primarily occurred in City of Jacksonville rights-of-way, roads, and easements. 

Restoration of the Project Area

Restoration of the project area typically begins 2-3 weeks after the project has been completed. Any existing grass, sprinklers, pavement, curb, gutter, driveways and/or sidewalks affected during construction will be returned to its pre-construction condition. 