Barnett Street Water Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2026-07-27
Anticipated End Date: 2026-09-18

Normal Work Schedule: 7:00 a.m. - 4:00 p.m.*
*Dates and times are highly subject to change. In some instances, extended hours or weekend work may be required.

Project Objective

As part of the Small Diameter Pipe Replacement Program to modernize hundreds of miles of JEA’s existing potable water distribution system, JEA replaced and upgraded a portion of the water line on Barnett Street between W. State Street and W. 1st Street

This section of water main had approached the end of its useful service life and is was proactively replaced to ensure the reliability of the JEA water system in the area. This project will provide increased water pressure and improved system reliability.

Construction Conditions

Construction primarily took place in the City of Jacksonville rights-of-way and utility easements.

Project Area Map

BarnettSt

Restoration of the Project Area

Restoration of the project area typically begins 2-3 weeks after the project has been completed. Any existing grass, sprinklers, pavement, curb, gutter, driveways and/or sidewalks affected during construction will be returned to their pre-construction condition.