Hernando Road Water & Sewer Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2025-08-18
Anticipated End Date: 2025-11-20

Work Hours: 7:00 a.m. to 5:00 p.m.*
*In some circumstances, extended hours may be required. 

Project Objective

A contractor working for JEA (JB Coxwell) replaced sanitary sewer lines, manholes, and a section of water lines at the intersection of Hernando Road and Marianna Road. This work is essential to maintaining the reliability of the water and sewer systems serving your neighborhood. When sewer lines fail, they can cause significant issues, including sewer backups, environmental harm, and roadway damage.

Construction Areas

Construction primarily occurred in City of Jacksonville rights-of-way, roads, and easements. 

Restoration of the Project Area

Restoration of the project area will begin typically begin 2-3 weeks after the project has been completed. Any existing grass, sprinklers, pavement, curb, gutter, driveways and/or sidewalks affected during construction will be returned to their pre-construction condition. 

Project Area Map

Hernando and Marianna Intersection Closure Map